Problem with P3EC
In the Open Standard
Jay HwayMember for 22 years 2 months
- Created
- 5
- 4
0
I’ve been playing around with P3ec after using P3.1 & Suretrak for the last year. P3ec does have some advantages, but I’ve run into some problems with the program. Most have been minor, such as only being able to put 1 curtain in the schedule or not being able to Print preview.
However, today I ran into a problem. I had done a monthly update (for the owner) for last month, in which I had statused an activity projecting to be 100% complete. However, because of circumstances the activity has yet to start. So when I go back to the schedule and try to unstatus the activity, P3ec won’t allow me to change the % complete. The only thing I can alter is the actual start and actual finish.
I talked to another scheduler and he said that Primavera 2.xx had a similar problem. Is there any way around this problem, besides deleting the activity and adding it back in?
However, today I ran into a problem. I had done a monthly update (for the owner) for last month, in which I had statused an activity projecting to be 100% complete. However, because of circumstances the activity has yet to start. So when I go back to the schedule and try to unstatus the activity, P3ec won’t allow me to change the % complete. The only thing I can alter is the actual start and actual finish.
I talked to another scheduler and he said that Primavera 2.xx had a similar problem. Is there any way around this problem, besides deleting the activity and adding it back in?
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?