Invalid Relationships & Not ideal critical path!

Jojie PepitoMember for 17 years
Created
3
2
0
Good day !

I need your help...

facts,

1. I have 800 activities on my scheduled project that mainly consist of 24 buildings and roadworks.
2. When i scheduled the project, there are 46 milestone activities which have an invalid relationships.
3. All this activities were completion activities which are linked to project completion.
5. Please advice me on how to resolve this problem.

and my expected critical path was not the one appeared on the scheduled project. Advice please!!!!!!!11

3 replies

Oldest first
  1. 0
    Anoon Iimos ·
    try using finish milestones and FF links (for invalid relationships)

    for expected critical path - try to use FS links (only!)
  2. 0
    Jojie Pepito ·
    Thanks for the reply!

    All the invalid relationships has an Finish milestone actvity type because it is all completion works.

    I need to determine the logical and real critical path but the result is very far from reality.

  3. 0
    Maghsoud Joudi ·
    Change your bar view to show float as well. You have some activities with no successor or long float which changes the critical path.

Log in or join to reply