Invalid Relationships & Not ideal critical path!
In the Open Standard
Jojie PepitoMember for 17 years
- Created
- 3
- 2
0
Good day !
I need your help...
facts,
1. I have 800 activities on my scheduled project that mainly consist of 24 buildings and roadworks.
2. When i scheduled the project, there are 46 milestone activities which have an invalid relationships.
3. All this activities were completion activities which are linked to project completion.
5. Please advice me on how to resolve this problem.
and my expected critical path was not the one appeared on the scheduled project. Advice please!!!!!!!11
I need your help...
facts,
1. I have 800 activities on my scheduled project that mainly consist of 24 buildings and roadworks.
2. When i scheduled the project, there are 46 milestone activities which have an invalid relationships.
3. All this activities were completion activities which are linked to project completion.
5. Please advice me on how to resolve this problem.
and my expected critical path was not the one appeared on the scheduled project. Advice please!!!!!!!11
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?