Drive Activity Dates by Default
In the Open Standard
Kaide Johar ManasiMember for 20 years 5 months
- Created
- 2
- 4
0
I loaded my schedule with Budget Quantities and created histograms. The BQ spread linearly as expected since the ’Drive activity dates by default’ setting on resource assignment option was selected. But I want to add labor resource (other material resource also) and the budget quantities are not spreading over the duration of activity. I have checked on my other computer, it is working. I exported in xls and for the new resource the original duration for it is zero. What must go wrong? is it SDK or a bug in P6. Any help in this regard would be highly appreciated.