Skip to content

Performance % complete

Dinesh Kumar DamavarapuMember for 24 years 7 months
Created
3
2
0
Hi all,

What is performance % complete in P3e and how it is calculated.

Thanks in advance.

Dinesh

3 replies

Oldest first
  1. 0
    Anwar Raza ·
    The performance % complete is the progress on the activity whatever defined as criteria for % complete for an activity.It gets rolled up on WBS level and gives you a picture on the WBS level if the projects are tracked based on physical percentage rather than duration or units.
  2. 0
    Dinesh Kumar Damavarapu ·
    Hi Anwar,

    Thank you for your reply.

    I have one activity with physical percentage as 40% while performance % is 41.67.Why is the difference and how it is being calculated.

    Thanks & regards

    Dinesh
  3. 0
    Anwar Raza ·
    Hi Dinesh,
    It is only applicable when the technique for activity % complete is enabled as "activity percent complete" in the earned value section of the wbs definitions.

    Regards

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?