Deliverable Activities
In the Open Standard
BB
Berli BerliMember for 24 years 3 months
- Created
- 18
- 2
0
For Engineering acitivities we usually use the deliverables which have 4 progress milestone of each deliverable (Start, Issued for Comment, Issued for Approval and Approved for Construction). For each milestone have individual weight factor such as Start 15%, IFC 50%, IFA 25% and AFC 10%.
Usually I make the s-curve from Excel spreadsheet, is there possible to make the s-curve from P3 with the progress milestone for each deliverable ? Because I have tried and the s-curve was differ from the reality...
Regards,
Berli
Usually I make the s-curve from Excel spreadsheet, is there possible to make the s-curve from P3 with the progress milestone for each deliverable ? Because I have tried and the s-curve was differ from the reality...
Regards,
Berli
18 replies
Oldest first- 0PJPhilip Jonker ·Hi,
Basically for example lets say your are casting a large concrete slab, this is normally done in a checkerboard fashion, in other words, in square of lets say 5m X 5m. For the fist half of the panels, you you would need shuttering, and the balance not, in my opinion a microschedule is a schedule drawn up in detail to determine the duration of all the panels in detail, to determine the duration of the whole slab, which can then be shown as a single activity, in the main schedule. In other words, it is detail scheduling to determine main activity durations.
Off-sets are used in resourcing, where different resources are used in thze execution of a single task. Lets say you are building a simple wall, ie excavate for foundation, cast foundation, brickwork. The sfirst resource would excavator, lets say one day, secondly concrete lets say one day, then curing, no resources say two days, and lastly brickwork say 4 days. The main activity, "build wall", would have a duration of 8 days. the resourcing would be as follows:
excavator duration 1 day offset 0 day
concrete duration 1 day offset 1 day
brickwork duration 4 days offset 4 days
Try drawing this on paper, and you will understand it.
Hope this helps.
Regards
Philip
- 0BBBerli Berli ·Dear All,
Thanks for your advice. I think the problem is Progress calculation in P3 for Delivereable or Engieneering Activities. Usually what Philip said we do that where in the Construction, Installation and Precom phase which is it can be measure by phisically.
I have tried for use the hammock activities with those progress milestone but it’s not efficienly i.e we have 1000 deliverable so we should develope and maintain for 4000 activities...
Warm Regards,
Berli - 0JLJaime Linchangco ·Hi,
You could still maintain your 1000 activities by defining a Resource Curve to spread its cost or resource unit over the duration of activity.
Add then Modify the resource curve value based on your deliverables weightage and distributed over time.
Once defined, assign this resource curve to each activities. Your S-Curve will correctly reflect the cost or resource distribution now.
Jaime
- 0PJPhilip Jonker ·Hi Berli,
I am sorry did not answer immediately, but spent some time in medical care.
You either have to detail your activities, or split them by resource, from my experience, it is easier to detail them, but ensure you add things like approvals and issudued for construction to your schedule, and then do not fall asleep, make sure you record every revision in your program, and ensure the client/managing contractor or whatevevr is aware of it, in time, early warning,
Regards
- 0BBBerli Berli ·Philips,
For monitoring the status and revision of documents/deliverables usually I use document database...
and Offcourse I use a milestone for relationship with Procurement, Fabrication and Installation due to Engineering is supporting them...
Jaime,
I have tried to using modified resource curve and only can be apply on the deliverable which have same interval of issue documents. For Example :
Start to Inter Discipline Review (5 days)
IDR to IFC (2D days)
IFC to IFA (35 days)
IFA to AFC (35 days)
Different type of document have different duration to prepare it, so usually duration from start to IFC is different for each documents...(Should we make some different resource curve...?)
Maybe to use the conventinal one (spreadsheet) is the better way and more eficient.. or we use P3 with the issue plan date using the Progress milestone...and the interval duration will be same for all documents.
Thanks...
Berli - 0JLJaime Linchangco ·Hi,
Yes, you may have a group of deliverables that differ with each other. At the planning stage, your deliverables maybe grouped as datasheets, procedures, P&ID, Calculations, Study Report, Plan & Details, etc. with equivalent or common duration and you may define a corresponding resource curve for each group.
Another possible way is through the use of "Steps". The new features in P3 e/c. I never tried it actually but it seems will work at the same case.
Those who using "Steps" already may share some experience in doing scheduling. Anyone?
Jaime - 0PGPuneet Gupta ·When using activity steps, First set % type as physical & click on the check box(Project window) for ACTIVITY PERCENT COMPLETE BASED ON ACTIVITY STEP.
Now say your deliverable is P&ID
Add P&ID as activity, define its step as
IFR
IFD
IFC
Define the step weightage for IFR, IFD & IFC
Then enter the % complete for the step, if IFR is completed then check in for completed.
I hope this may be clear to you. - 0SKSunil Kumar ·When i am creating a deliverable schedule.. do i need to give for each each deliverable 4 separate activities( like start,IFR,IFD & IFC) under each deliverable.... how to go about it...
say if i have got 1000 deliverables then 1000 Wbs has to be created & 4000 activities will be generated
& how to assign resource for that deliverables
has anybody done this.
sunil - 0OGOmar Grant ·An interesting discussion but I have always worked within systems where, with large numbers of deliverables the detail (Level 4) control of engineering deliverables and their weighted progress/forecast completion dates is managed within a separate database, under the operation of the Lead engineers. The connection to the schedule is a manny (deliverables) to one P3 discipline activity ’engineering work pack’ which is related to an MR or a construction workpack. The connection is the P3/P6 activity ID. Progress is rolled up in the data base with a % progress and the latest forecast completion date of all deliverables in the EWP gives the driving date for the issue of the MR/Work Pack. This method allows effective sequence & time management without creating huge schedules.
- 0TRTomas Rivera ·Omar,
What if you want to link Issued for Review drawings to Get Construction Permit, and link Issued for Construction drawings to Request for Proposal, and link Approved for Construction drawings to Start Construction. All of this for the diferent work packages. You would need to have everything inside your schedule without using an external database.
Tomas Rivera
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?