P3e Report - Resource Assignment

Shahrol SabaruddinMember for 21 years 8 months
Created
0
2
0
Questions:-

1.In P3e report, under Report Group:Report Usage, RA-01 Resource Assignment, All Activities, how do I filter for only outstanding activities, meaning 0% to 99% completion? Default will show 0% to 100%.

2. In one activity there’s two resources. How do I separate in report, let say Resource 1 with Activity 01 and Resource 2 with Activity 01? What I got is in the report Resource 1, Resource 2 with Activity 01 (default feature, i think so). I could do this in P3 but in P3e, i couldn’t find a way around it.