Changing Defaults

Alan CallowMember for 21 years 10 months
Created
4
21
0
Anyone know how I can change the default settings to:

a. Activity type = Resource dependent/Finish milestones/Start milestones
b. Duration type = Fixed duration and units/time
c. % Complete type = Duration

4 replies

Oldest first
  1. 0
    Steven Oliver ·
    In the Enterprise view, look at the default tab on the bottom layout.



    HTH


  2. 0
    Alan Callow ·
    Thanks
    Although Admin Superuser I have to change defaults project by project. In enterprise view the choices are blanked out, any thoughts
  3. 0
    Kevin Button ·
    These are project level settings so unfortunately you are stuck with it. Cheers
  4. 0
    Alan Callow ·
    Many Thanks for the help