Progress Spotlight
In the Open Standard
Bijaya BajracharyaMember for 21 years 7 months
- Created
- 2
- 1
0
P3 used to have a very good feature of progress spotlight whereby you could highlight where to exppect progress. I have not found a similar feasure in P3e/c. There is a feature "updating progress automatically" which can update the prgress automatically but it does not highlight and display the activities. Strangely in the help feaure of the "updating progress automatically", there is mention of View, Progress Spotlight. But this feature is not there. Can someone clarify it?