Exporting from P3 e/c to P3

Mirza Imam BaigMember for 23 years 5 months
Created
3
2
0
Hi Planners,
Greetings

I prepared the Baseline Design Schedule in used P3 e/c. I am listing down few of the Activities of the Schedule below. My planning Unit is “Day”. and the Calendar is 5 day Calendar with Sat, Sun, Mon, Tue and Wed as Working days and Thursday and Friday as Non-working days.

In P3e/c

S. No. Activity Description Orig. Duration Early Start Early Finish

1 Mechanical Design 114 d 26-Dec-05 08-Jun-06
2 Electrical Design 106 d 05-Jan-06 08-Jun-06
3 Structural Design 81 d 13-Feb-06 08-Jun-06


Later the Client asked us to generate the same schedule in P3. So I exported the schedule from P3 e/c to P3. After exporting, I experienced lot of inconvenience due to the changes in dates and durations. I am listing down the same activities in P3 (after exporting)

In P3

S. No. Activity Description Orig. Duration Early Start Early Finish

1 Mechanical Design 143 26DEC05 12JUL062
2 Electrical Design 133 09JAN06 12JUL06
3 Structural Design 101 22FEB06 12JUL06

I could not understand why this happened. When I checked the calendar in P3, it shows the same working days and non-working days as that of P3e/c.

Can anyone help me on this….. Why this happened and how to overcome this kind of problem in future.

Thanks.

3 replies

Oldest first
  1. 0
    Henk van der Heide ·
    Imam,

    I think you’ve a calender problem
    Best way to find out: Check both durations in Hours.
    It seems that 1 day is not always 8 hours work. (this can be the problem).

    Regards

    Henk
  2. 0
    Alan Callow ·
    Under Admin > Admin Preferences > Time periods > check the default time this may affect duration unless shown in hours
  3. 0
    Mirza Imam Baig ·
    Hi friends,

    Thanks for the response

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?