A colleague of mine has asked the following question:

’I am puttng progress in a plan which is not baselined at the moment. Is there a way we can reflect the progress for each activity as a cumulative % at the WBS level without using WBS milestones? As at the moment when I collapse all the activites at the WBS level, the bar doesn’t reflect the progress of the activities underneath.’

Does anyone know the answer ( I don’t know why he isn’t using a baseline btw

1 reply

Oldest first
  1. 0
    Puneet Gupta ·
    Use performance % complete to see the progress at WBS level