Skip to content

Resource Assignment Layout

Shahrol SabaruddinMember for 21 years 8 months
Created
2
3
0
How to get only oustanding or in progress (Physical % Complete between 0% to 99%) Resource Assignment layout in P3e. I’m using P3e 3.5.1 by the way.

I’ve tried but it’ll will shows Resource Assignment with all activities including 100% complete. Could somebody help me.

2 replies

Oldest first
  1. 0
    Niek Zonneveld ·
    Shahrol,

    100% complete activities have an actual finish, so if you filter on: "actual finish equals [empty]" you’ll get what you are looking for.

    Cheers,

    Niek.
  2. 0
    Shahrol Sabaruddin ·
    Thanks, Niek. It help!

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?