Budgeted Costs
In the Open Standard
Andy QuinnMember for 21 years 4 months
- Created
- 2
- 3
0
Hi all
I have assigned budgeted costs to my activities (non labour) but every time I make the start date an actual the cost totally disappears!
If the cost is a labour cost then I do not have the same problem.
Has anybody else had the same problem or does anyone have a solution.
Thanks
I have assigned budgeted costs to my activities (non labour) but every time I make the start date an actual the cost totally disappears!
If the cost is a labour cost then I do not have the same problem.
Has anybody else had the same problem or does anyone have a solution.
Thanks
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?