Budgeted Costs

Andy QuinnMember for 21 years 4 months
Created
2
3
0
Hi all

I have assigned budgeted costs to my activities (non labour) but every time I make the start date an actual the cost totally disappears!

If the cost is a labour cost then I do not have the same problem.

Has anybody else had the same problem or does anyone have a solution.

Thanks

2 replies

Oldest first
  1. 0
    Bill McMichael ·
    I cannot think of a scenario that would reset the task’s budget to zero by simply statusing the task with an actual start date.

    Here is a place to start.

    1. Go to the Project’s Screen , select your project in question , and then go to the Calculations tab (located at the bottom of the screen). This tab contains settings that impact activity and assignment calculations. Perhaps you will notice a setting here that is not configured the way you would like.



    Regards,
    Bill
  2. 0
    Alex Wong ·
    The only think I know to remove non labor budget is reverse status for Actual Finihsed activity.

    R U sure it is associated with Start date??

Log in or join to reply