HELP P6 Budgeted Labor Units Suddenly Changed!!!
In the Open Standard
CO
Civ OczalevMember for 17 years 9 months
- Created
- 14
- 9
0
14 replies
Oldest first- 0AMArmando Moriles ·Civ,
I think you have to be careful with your Activity Duration Type.
Fixed Units/Time
1. If you change duration, your units changes
2. If you change units/time, your duration changes
3. If you change units, your duration changes
Fixed Duration and Units/Time
1. If you change duration your units changes
2. If you change unis/time, your units changes
3. If you change units, your units/time changes
Fixed Units
1. If you change duration, your units/time changes
2. If you change units/time, your duration changes
3. If you change units, your duration changes
Fixed Duration & Units
1. If you change duration, your units/time changes
2. If you change units/time, your units changes
3. If you change units, your units/time changes
hope it helps...
Arman - 0DWDieter Wambach ·Civ
Activities were started?
View Projects, tab calculations: "Update units when costs change on resource assignments": Mark this checkbox for the Project Management module to recalculate units when costs are updated for the assignment. Cost changes, such as modifying the remaining cost for activities, cause the Project Management module to recalculate units. (from P6 Help)
Did you ever consider a training?
Regards
Dieter
- 0AIAnoon Iimos ·I believe your name is Vic. So Vic, the schedule is supposed to be dynamic thus it depends on the chosen parameter. My advise is, the only thing that you need to fix is the work units or quantity of work, the rest i.e. manhours (labor), duration, are supposed to be flexible.
Quantity of work is supposed to be defined in the "scope", BOQ or in the "contract". Changes or variations with regards to the quantity of work is another story. - 0COCiv Oczalev ·Please advise this situation regarding this problem:
Apparently, someone changed global settings. So, all my activity duration on the BASELINE schedule was reduced by 80%. And with that, the budgeted labor units as well.
Is there a fix to this? Can I change the global settings so I can revert back to the original duration and labor units?
PS This incident was brought about by all of us having ADMIN access. - 0DWDieter Wambach ·Civ/Vic?
Reduce admin rights!
Baseline: Was it created as a baseline and attached to the project or was it a copy of your project? In the first case it shouldn’t be touched by scheduling and a modification of calendar settings.
Please explain more in detail.
Regards
Dieter
- 0COCharleston-Joseph Orbe ·At first thought his name seems foreign sounding as if some Turks from turkey.
But very seldom we will encounter such a name in Philippines.
Now I know, the guy spell his name backward.
It is Vic Velasco.
This is an example of analytical mind. The hallmark of a great forensic planner.
Cheers,
Happy Planning and Scheduling - 0COChris Oggham ·Charlie,
I can’t understand why it’s taken your "analytical mind"? this long to come up with that. Anoon picked it up straight away (see post #8) the clue Charlie is in post #1, victov@dtmt.com.au his e-mail address.
Before you make self-congratulatory remarks on your analytical mind or your supposed forensic planning abilities, you really ought to try reading the posts. If nothing else it would stop you making a complete clot of yourself.
Chris Oggham
- 0COCiv Oczalev ·Dieter,
Yes I attached the baseline to all the project updates. Any solution you can think of? What global changes would have been done to reduce original duration and budgeted labor units to 80% of what it was?
I attended basic P6 course. $3000. Well basic did not tackle this. :-) - 0DWDieter Wambach ·Vic
With a global change, you can’t access the baseline while it’s assigned to the project - only by restore --> modify --> assign.
It would be possible by SQL-program. As far as I know no direct means. For my opinion there must be a different mistake.
If you have a chance, show your plan to an experienced planner.
In a three days training you can’t cover all items.
Good luck!
Dieter
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?