on tracking

Francis Moyalan, PMP,PMI-SPMember for 21 years 8 months
Created
4
2
0
hi,
can any body help by explaining me how to do the tracking in a project....

along with that can any one help me by telling the new versions of primavera and it’s various applications...

4 replies

Oldest first
  1. 0
    Mk Tse ·
    Francis,
    Brochures and lot of application cases are available on Primavera website.
  2. 0
    Sukumaran Subaramaniyan ·
    Hi,

    What do you mean by HOW TO DO THE TRACKING IN A PROJECT?
    Is it MS Project schedule or P3e schedule.

    Regards.
  3. 0
    Dayanidhi Dhandapany ·
    Tracking:

    1. Establish baseline programme.
    2. Distribute monitoring sheets to relevant supervisors(capture the relevant information you need to update schedule)
    3. Set up the periodical updating date before which u need to receive the item 2.
    4. Update the schedule(use baseline your target to check for any slippages)

    in the next update, use the prev. update as your one of target schedule to verify any activities slipped from the completion dates, check over all project completion date...

    many more things to add............


  4. 0
    Anand Kulkarni ·
    Few more...

    Schedules are mainly tracked on three things

    1)Time
    2)Resources i.e. Man, Material,Money
    3)Site Inspection

    The presentation of the these parameters can be done in many forms depending on the level at which are to be presented.

Log in or join to reply