i am working for the owner and i want to applying EV concept in my monthly report for tracking schedule,cash flow status (interim payment preparing and approving). My question is:
_ for BCWS, i can use BOQ and construction schedule from Contractor for updating and entering to my program.
_for BCWP, i can tracking actual work by monthly
_ but for ACWP, can i use interim payment claim from Contractor?or where it come from that i can use for define ACWP.
we have formular : SV=BCWP-BCWS => i can only assess schedule status without
CV=BCWP-ACWP => no data with ACWP mean i can not assess Cost status???
_ for BCWS, i can use BOQ and construction schedule from Contractor for updating and entering to my program.
_for BCWP, i can tracking actual work by monthly
_ but for ACWP, can i use interim payment claim from Contractor?or where it come from that i can use for define ACWP.
we have formular : SV=BCWP-BCWS => i can only assess schedule status without
CV=BCWP-ACWP => no data with ACWP mean i can not assess Cost status???
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?