Peak Usage for Resource Loading in P3e/c

Vamsi KolliboinaMember for 25 years 1 month
Created
2
2
0
Hi All, I used take the Peak Usage of Resources from the Resource Loading Report. I am unable to do the same with P3e/c anymore. I hope they add this functionality in their next release. In the mean time is there any easy workaround ? Cheers, Vamsi

2 replies

Oldest first
  1. 0
    Alex Wong ·
    Vamis

    One work around is to use resource table by date
    Export the table to Excel run a function to select the max from each week/month/quater.

    That should give u a table with peak resource usage @ the time period you wanted

    Cheers

    Alex
  2. 0
    Vamsi Kolliboina ·
    Alex,

    Yeah,I am importing the data into excel right now.But its bit tedious when u have to do a Weekly Peaks report for a project with duration of 24 months. I hope primavera will add this feature in the ver.5(I have pointed out this to them,anyway)

    cheers,
    vamsi