Filtering Relationship Lags

Jihad DanielMember for 21 years 5 months
Created
5
2
0
Dear All,

Do you know a way to do a filter to search (for example) for negative lags in a schedule?
In Claim Digger, the report shows relationship Id# and relationship lag, can these be used in a way or are only indicative?

Thanks & Regards,
J.S. Daniel

5 replies

Oldest first
  1. 0
    Bill McMichael ·
    If you want to get a listing of negative lag relationships, one way to get this is by creating a report.
    Create a report with subject area activity relationships, show columns you are interested in, and you can filter where lag < 0.

    Regards,
    Bill
  2. 0
    Jihad Daniel ·
    Dear Bill,

    How can you create a report with subject area "activity relationships" not defined in P3e? And customizing this data is not wise thing to do.

    Regards,
    J.S. Daniel
  3. 0
    Bill McMichael ·
    If you are asking how to create an activity relationship report, here’s how you do it.

    1. On reports screen, click Add
    2. Choose Activity Relationships as subject area
    3. Choose fields you are interested in seeing.
    4. Set filter as Lag < 0.

    If you are asking something else, please rephrase.

    Regards,
    Bill
  4. 0
    Mohamed Hegab ·

    Schedule Cracker

     

    Schedule Cracker (www.schedulecracker.com) provides what you are looking for.  We identify lag through relationships, filter them or group activities by lag and much more.  Our powerful tool allows you to compare multiple schedules, trend project-performance values, and forecast project performance, and much more.

  5. 0
    Raymond Au-Yeung ·

    Dear Jihad, There should be

    Dear Jihad,

    There should be no way that can filter out lags as lag is a data between a predecessor and a successor. That means it involve two activities. Hence in one activity you cannot find 'lag' as a filterable data.

    Using report to search is a way to do it.

    Regards and happy reporting,
    Raymond Au-Yeung

Log in or join to reply