Early/Late work/cost distribution

Joao RibeiroMember for 23 years 6 months
Created
3
2
0
When reporting in P3, there are options to report work/costs using early, late schedule dates or a mix of both.
I have been trying to find something similar in P3e/c 4.1, but it looks like that the only thing its reporting module does is an early dates distribution.
Any comments or sugestion to overcome this problem?

Thank you.

3 replies

Oldest first
  1. 0
    Steven Oliver ·
    In the Resource Usage spreadsheet view, there are a number of options (Spreadsheet Fields, Customise). Use this view as the basis of a report.


    HTH


  2. 0
    Joao Ribeiro ·
    Thank you, I think it will do what I want, with a some costumization...
  3. 0
    Henk van der Heide ·
    Joao,

    Late dates cant be done right away,
    If you need them let me know i’ve a work around. (in primavera)

    Regards

    Henk