How to create Cumulative Late Curve in P6
In the Open Standard
PY
Paul YoonMember for 22 years 1 month
- Created
- 129
- 6
0
I am trying to find out how to generate a cumulative Late Curve and cumulative early curve for my cost loading/cash flow in P6. However I still don’t know how to do it.
In P3, there is an easy step under tool (report tool) to display both of them, but in P6 where???
Or could you teach me how I can extract cost loading data based on late start date into excel? Then I can generate a cumulative late curve.
Thanks in advance.
In P3, there is an easy step under tool (report tool) to display both of them, but in P6 where???
Or could you teach me how I can extract cost loading data based on late start date into excel? Then I can generate a cumulative late curve.
Thanks in advance.
129 replies
Oldest first- 0APArnold Puy ·Hi Paul,
If you can do this in P3 you can also do this in P6. The same steps but different approach.
You must create two baselines in one project.
1. Baseline (Early Planned)
2. Late Planned
After creating these two, assign them. The first one as Project Baseline and the second one as Primary.
Try this and I will tell you what to do next.
Regards,
Arnold - 0KMKarim Mahgob ·Go to the resource profile and right click then choose- Resource usage profile option in the Data section..
Choose Cost to display and also mark check box of remaining early & remaining late.
Then mark the resources in the left pane..you’ll find the graph for remaining early and late
Try to do this exersice and let us know the result - 0APArnold Puy ·Hi Guys,
I already sent to your email. But please if you have something in detail try to share to others.
I know most of the Planners need your assistance. It’s up to you to comments my WORK. But this is my initiatives & ideas on how to show the Early & Late Curve in P6.
Thank you.
Regards,
Arnold - 0DHDiego Henriquez ·I have not try this in P6 yet, but It should work.
If you make a copy of your current schedule and by using global change you constrain all your activities to be completed as late as possible, then all your resources will be allocated to the latest possible date.
I do not believe purely on early and late curves tho, probability of an schedule is the most important subject to asses if the early and late curves are healthy... - 0KZK Z ·Hello Arnold,
Please I have a question concerning earn value. I have already set my my earn value programme, I only track man-hours.
Using P6 I was able to set up my layouts, but I could not get the field: To complete performance Index- Labour units, but there is To complete performance Index for cost.Is it that primavera does not have that field.
I will appreciate if you can help.
Thanks for your assistance so far.
Rgards,
Keme