% completion link/unlink RD and Actuals
In the Open Standard
Rashid IqbalMember for 21 years 5 months
- Created
- 4
- 2
0
Hi,
I want to arrange the ’settings’ so that when activties are updated for % completion, the actuals for the resources and the RD is automatically calculated. And is it possible that for some activties in the same schedule I could unlink the % completion from the resources actual and RD.
Any help would be highly appreciated
Regards
Rashid
I want to arrange the ’settings’ so that when activties are updated for % completion, the actuals for the resources and the RD is automatically calculated. And is it possible that for some activties in the same schedule I could unlink the % completion from the resources actual and RD.
Any help would be highly appreciated
Regards
Rashid
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?