Remaining Late Units is showing before Data Date & after completion of the Project...why ?
In the Open Standard
Irfan KhanMember for 17 years 3 months
- Created
- 10
- 9
0
Dear all,
I am preparing my Recovery Schedule now & one of my consultant asked me to prepare a mean curve i.e. 60% from Early Unit & 40% Late Units.
In this regard my Data Date of the Schedule is 12-Sep-2014 & when i am looking @ my Remaining Late Unit its shows units distributed in the month of July & August 2014, furthermore my completion of the project is 30-June-2015 even though the units are showing in the month of July 2015 as well.
I have checked that non of the activity having negative float & i have applied the constraint on my Milestones but the units are still showing beyond the limit.
any help in this regard will be highly appreciated.
thanks
10 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?