Copying Activities

Conrad ArellanoMember for 25 years 8 months
Created
3
1
0
Hi,

If I copied a group of activities and paste them in another group, P3e does not follow or match the original activity ID order.

Example:
10 activities (AB010, AB020, AB030, ...AB100)

When pasted into another section/group in the schedule, P3e will generate (using prefix CD) CD010, CD020, CD030...CD100 However, CD030 does not match AB030, or CD050 with AB050.

Does anybody encountered this kind of problem. Thanks for any info.

3 replies

Oldest first
  1. 0
    Kevin Button ·
    Something to try - at the project level, select the Defaults tab and set your auto numbering defaults to what you need.

    Hope this helps.

    KB
  2. 0
    Hazel Mendez ·
    Hi,

    I would like to clarify where you paste the activities.Are you trying to paste it in the same "Project" but different "group"?
    If so, you could try to "cut" the activities instead of "copy". This is because activity ID must be unique, so if you try to "copy" activities and paste to another group Primavera will not allow duplication of ID’s so it tends to create new ID’s based on your ID numbering options.

    Hope this will help,


    Hazel
  3. 0
    Niek Zonneveld ·
    C.A.

    Project Manager copies activities in the sequence you select and then pastes activities in that same sequence; according to the First-In First-Out principle.

    So if you sort by Activity Name (instead of Activity ID), and then select the activities to copy, it will also paste activities in that sequence. With that paste (and "B" as Activity ID Prefix) it will automatically renumber the activities with the increment selected (i.e. B1000, B1010, etc.)

    The end result is that A1000 will not (necessarily) match B1000, and A1010 can be a different activity than B1010, etc.

    So if you first sort by Activity ID and then do copy & paste, it should work as you prefer.

    Cheers,

    Niek.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?