PROGRESS CURVE IN P3 ec ?
In the Open Standard
Q ZhouMember for 21 years 2 months
- Created
- 0
- 1
0
I am a new user of p3 ec v41.
when i divide the contract value to activities ( weightage) , i treat the weightage as a resource and keyed the numbers in.
then i get a s-shaped curve which is used as the target.
however, everytime I update the schedule, I get the actuals, remaining early and remaining late bars(both from zero again, it is so difficult when using these curves to evaluate progress and make forecast using such curves. is it possible to add the remainings to the actuals graphically in P3 EC or is there an easy way to export the data to excel and make the curve in excel?
anybody can help me to get the best way to handle this issue?
thanks.
when i divide the contract value to activities ( weightage) , i treat the weightage as a resource and keyed the numbers in.
then i get a s-shaped curve which is used as the target.
however, everytime I update the schedule, I get the actuals, remaining early and remaining late bars(both from zero again, it is so difficult when using these curves to evaluate progress and make forecast using such curves. is it possible to add the remainings to the actuals graphically in P3 EC or is there an easy way to export the data to excel and make the curve in excel?
anybody can help me to get the best way to handle this issue?
thanks.
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?