Activity Starting Hour

Conrad ArellanoMember for 25 years 8 months
Created
3
2
0
Hi,

I set-up the calendar for an 8hrs/day with work starting at 8:00am. However, everytime a Start On or After contraint is assigned to an activity, P3e/c calculates the activity to start at 12:00noon.

What should be the setting to have the activity starts on 8:00am after assigning a Start constraint.

Thanks

3 replies

Oldest first
  1. 0
    Niek Zonneveld ·
    By default Primavera is using the start time of the activity as the (start) constraint time.

    If you want to change that default value you should override it manually for each constraint. (make sure you can see/edit time by selecting the right user preferences)

    HTH

    Niek.
  2. 0
    Se de Leon ·
    Hi Conrad,

    Se here.

    One possibility: have you tried scheduling it first after you entered the activities? Entering the activities at first, P3ec will show a default time. Try scheduling it then you will see the correct time.

    2nd possibility: Change the time in the current data date.

    I hope this will help.

    Ingat ka lagi diyan.

    Se
  3. 0
    Conrad Arellano ·
    Thanks Niek & Se for the reply.

    The only way I can set the start of the activity at the correct hour is to edit it manually or change the timescale to hours and drag the start of the activity.