Price / Unit Time in Resource Tab

Amar AghanaMember for 21 years 2 months
Created
2
14
0
I have created a new currency in

Admin >> Currency >> Omani Riyals OMR

Then

I have created a resource say Engineer

Then

I have assigned Omani Riyals in Curency and Overtime by Enterprise >> Details >> Curency and Overtime

Then

in Unit & Prices, I wish to enter Omani Riyals OMR10/h but it is apprearing $10/hr.

Please advise how to make OMR10/h

Thanks in advance.

2 replies

Oldest first
  1. 0
    Bill McMichael ·
    To set currency preferences, go to
    Edit / User Preferences / Currency.


    Regards,
    Bill
  2. 0
    Amar Aghana ·
    Bill, Thanks, It works. - Amar.