P3 e&c Stand Alone & Data Transfer

Amar AghanaMember for 21 years 2 months
Created
8
3
0

We have 2 numbers of P3 e&c Stand Alone softwares to handle around 200 on gooing projects.

The one software (say S1)is installed in HO

and

The other software (say S2)is installed at Site.

S1 : is supposed to take care of Engineering with one planner

S2 : is supposed to take care of Procurement and Construction with another planner

Our conditions are

1)Activities of Engineering to be created / updated in S1

2)Activities of Construction to be created / updated in S2 taking and linking datas from S1 for engineering.

What is the best and easiest way to exchange the datas in this case for around 200 ongoing projects so that all datas are available simultaneously in S1 and S2.

3) Please do not suggest to go for web based server version as these softwares are already purchased.





8 replies

Oldest first
  1. 0
    Steven Oliver ·
    Have a look at Check In/ Check Out.
  2. 0
    Amar Aghana ·
    Steven, I think you are suggesting for e&c installed on server. I have problem in sending projects to site and receiving the updated project from site. Do you advise, this is still possible with Check in / out for standa alone versions? Need little more details please.
  3. 0
    Amar Aghana ·
    Steven,

    With manual I could make them work. Thanks.

    Is there any way to use filter for check in and check out.
  4. 0
    Steven Oliver ·
    From the P3e (not very helpful) help.

    You can "check out" projects so that they can be worked on remotely. Once a project is checked out, it can no longer be modified until it has been checked in. In addition to checking in the project, you may replace the existing project with the remote copy of the project by using the Import wizard.

  5. 0
    Jose Frade ·
    Hello Hamar

    The best solution is:

    Creat the project structure in such way that the sub-projects are organized by project phase:

    Ex: Main proj: PROJ01
    Sub: -ENG1 (Engineering)
    Sub:- PRCO (Procurement/Construction))

    The idea is:
    Each site opens just the subproject is entitled to work with, even though he can see the other activities and suffers impacts from others.

    the update is simple: The site taking care about the subproject send a backup to the other. The restore of the backup immediately updates the global project (after rescheduling).

    Best regards
    JMFrade

  6. 0
    Amar Aghana ·
    Hi Jose,

    Thanks for your participation. I was using the same technique all the way from P3 Ver 2.0, 3.0 and 3.1.

    Do you think it is possible in Ver 4.1 e&c ??

    I have not understood sub project concept in e&c . can you please explain in detail?
  7. 0
    Jose Frade ·
    Oops

    I did not see the referenc to e&c.

    I can only advise towards P3.

    BR
    JMFrade
  8. 0
    Amar Aghana ·
    Never mind. Fully appreciate your intention of helping others.