transfer EPS from P3e to P6

Tamer SayedMember for 20 years 8 months
Created
11
2
0
dear friends
does any one know can i transfer EPS from P3e to P6

i worked before on P3e i created before EPS not i want to install P6 what can i do to transfer this EPS from P3e to P6

Note :-
i try used with Export from P3e to P6 and import using P6
but with this way i should export 1 project per time

if any one have any solution please let me know
thank you

11 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Tamer
    P6 is the current version of P3e. On your cd’s you can find scripts to upgrade your database to P6.
    Study the readme-files first!
    It is not possible to migrate directly from P3e 4.1 to P6. Even P6 and P6.1 has a different database - and the migration requires an upgrade.
    Good luck!
    Dieter
  2. 0
    Tamer Sayed ·
    Dear Sir
    thank you for your sooner replay
    could you please tell me steps in details
    cause i do not know more about primavera and database
    so please tell me from where this scripts and readme
    thank you
  3. 0
    Dieter Wambach ·
    Tamer
    Among your installation CD’s on the first you can find the script for update from previous version. CD 3 is the documentation CD with an admin manual. Please read this first. If you don’t understand, it will be better to let your IT staff do it or to enter EPS and OBS by yourself. The risk to destroy data would be too big.

    XER file can contain many projects.

    Good luck!
    Dieter
  4. 0
    Tamer Sayed ·
    Xer files contain 1 project only
    if i export more projects in export screen i should click in only 1 project

    any way tell me how can i transfer many projects by xer files

    thank you
    sorry for distribing
  5. 0
    Dieter Wambach ·
    Tamer
    No disturb. If you’ll open more projects you can export them in one file. just select all projects within the export wizzard.
    Dieter
  6. 0
    Tamer Sayed ·
    ok thank you
    but please tell me how can i reach for database file to transfer EPS
    really i am in critical position
    please help me in this subject
    tell me in steps please
    i can do every thing
    and no IT here
    i do all jobs
    if i can not do this may be it will be not good for me
    thank you
  7. 0
    Dieter Wambach ·
    Tamer
    In Most installations the EPS isn’t big. It’s faster to type in the new db than to write a script. For a script you’ll need IT and access to to (AND knowledge of) Enterprise Manager.
    Dieter
  8. 0
    Tamer Sayed ·
    Dear Sir
    could you tell me what i will do after i find this file ssmee.exe
    i found this file ion my pc cause i use SQL in my pc but tell me how can i use it

    but i can not find this file on my pc in job cause my company use Oracle system

    So could you please which file i will use in Oracle System to copy EPS

    Thank you
  9. 0
    Tamer Sayed ·
    Dear Sir.
    our database working under ORACLE
    so could you please let me know which file i can use to transfer EPS from P3e to P6
  10. 0
    Dieter Wambach ·
    Tamer
    The data model is the same under ORA and MS SQL. For an upgrade from one to the other you’ll need a specialist from your Primavera rep. For upgrade have look into your CD no.3 Documentation --> technical ... --> manual upgrade.
    Within the technical documentation you can find the schemas of all tables and a printout in A0-format of the data model.
    For the EPS have a look into the table PROJECT, data item "project_flag", which indicates if a record idenfities an EPS-node or a project.
    Hope that helps!
    Dieter
  11. 0
    Dieter Wambach ·
    Tamer
    Sorry, I don’t know this file ssmee.exe.
    Regards
    Dieter

Log in or join to reply