Q ZhouMember for 21 years 2 months
Created
3
2
0
On Page 124 of the operator’s manual there is a paragraph

"you can view the entire WBS at once, or you can display only the WBS for a specific note or project".

I can ONLY display the WBS of openned project, Is there any setting to resolve this issue?

3 replies

Oldest first
  1. 0
    Kevin Button ·
    You can only vew the WBS for projects that are open and there are no settings to get around this.

    Regards
  2. 0
    Stephen Hart ·
    another work around is to create a specific project within EPS structure containing the entire wbs.

  3. 0
    Suraj Bhatt ·
    For managing Projects ,there is an EPS .For managing Project, there is a WBS.
    Why do you want to see WBS for full EPS?
    Regards,
    Suraj