Reviewing a contractor's monthly P6 update: what do you check first?

BilingualpmoMember for 0 months
Created
4
234
0

Every month the same job: compare this month's XER against last month's, find out why the finish date moved, and write it up for the PM or the client.

My checklist, in order:

  1. Finish-date movement, and which activities drive it

  2. Deleted or changed relationships on the critical and near-critical paths

  3. Durations cut or grown with no basis given

  4. New hard constraints (Mandatory Finish, Finish On or Before) that hide negative float

  5. Activities that slipped but gained float (usually a sign logic was removed)

  6. Out-of-sequence progress and actuals after the data date

  7. Whether the narrative actually explains what the XER shows

What would you add?

4 replies

Oldest first
  1. 0
    Garson Hill ·
    • Has the finish date moved? If yes, why?

    • What's newly critical this month?

    • Has any work been aded or removed?

    • Does the reported progress look believable?

    • Have any major milestones changed?

    • Do the schedule and the written narrative tell the same story?

    For me, the key question is always: "What's changed since last month, and does it make sense?" Everything else is usually supproting evidence.

  2. 0
    Bilingualpmo ·

    Thanks, that's a good way to frame it. 'Does the progress look believable' is the one I see skipped most: physical % jumping while remaining durations barely move. Do you check that against the field reports, or just against last month's trend?

  3. 0
    Ramesh ·

    Good list. A few I'd add, because they move dates without touching logic or durations:

    • Calendar changes. An edited activity or project calendar (holidays added, workweek changed) shifts dates with no visible change in logic or durations.

    • Scheduling options. Retained Logic switched to Progress Override, or the critical path definition changed between Total Float and Longest Path. Check the F9 settings before comparing anything.

    • Lags. Lags added, removed or shortened on critical links. They're easy to miss in a relationship comparison.

    • Baseline assignment. Make sure the project baseline is still the approved one and hasn't been swapped for a newer update.

    On believable progress: I check against field reports where quantities exist. Where they don't, I compare the implied rate. If an activity went from 40% to 70% this month but its remaining duration only dropped from 30 to 25 days, the % or the duration is wrong. Trend alone mostly confirms whatever was claimed last month.

  4. 0
    Bilingualpmo ·

    Thanks Ramesh, those are good additions. Calendars and the F9 settings probably belong at the top of the list, because a relationship comparison shows nothing when either one changes. On calendars I'd check which calendar each activity is assigned to as well as the calendar definitions. Moving a critical activity onto a 6-day calendar shifts the date just as quietly.

    Good point on lags too. A lag cut from 10 days to 3 looks like the same link unless you compare the lag value.

    I like the implied-rate check. 30% progress for 5 days off the remaining duration is easy to put in front of a contractor. Do you set a tolerance before you raise it, or do you query every mismatch?

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?

Knowledge

Discussions

Blogs

Jobs