Reviewing a contractor's monthly P6 update: what do you check first?

BilingualpmoMember for 0 months
Created
0
28
0

Every month the same job: compare this month's XER against last month's, find out why the finish date moved, and write it up for the PM or the client.

My checklist, in order:

  1. Finish-date movement, and which activities drive it

  2. Deleted or changed relationships on the critical and near-critical paths

  3. Durations cut or grown with no basis given

  4. New hard constraints (Mandatory Finish, Finish On or Before) that hide negative float

  5. Activities that slipped but gained float (usually a sign logic was removed)

  6. Out-of-sequence progress and actuals after the data date

  7. Whether the narrative actually explains what the XER shows

What would you add?

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?

Knowledge

Discussions

Blogs

Jobs