Work Column in P3e/c
In the Open Standard
Brian CameronMember for 22 years 5 months
- Created
- 4
- 3
0
Hi
I was wondering if anyone could give a novice some guidance.
I have just recently had P3e/c installed and I have imported a couple of MS Project 2003 schedules which typically showed the following columns "Name", "Start", "Finish", "Duration", "Work" and "Cost".
What I would like to see is a layout / column which shows "work" (hours).
I normally have the duration and work columns sitting next to each other and they could be multiples of 8 hr’s or it could be 10 days duration and only 3 hr’s of work, i.e. updating a report spreadsheet over 2 weeks, not necessarily everyday.
With MSP this is all readily visible on the screen.
For some new schedules I sometimes use an old one and remove the resources (some may have moved on) so when I give a manager a hard copy he can see all the information he needs to see and only has to assign persons to tasks.
Is there a simple way to do this in a similar fashion??
Regards
Brian
I was wondering if anyone could give a novice some guidance.
I have just recently had P3e/c installed and I have imported a couple of MS Project 2003 schedules which typically showed the following columns "Name", "Start", "Finish", "Duration", "Work" and "Cost".
What I would like to see is a layout / column which shows "work" (hours).
I normally have the duration and work columns sitting next to each other and they could be multiples of 8 hr’s or it could be 10 days duration and only 3 hr’s of work, i.e. updating a report spreadsheet over 2 weeks, not necessarily everyday.
With MSP this is all readily visible on the screen.
For some new schedules I sometimes use an old one and remove the resources (some may have moved on) so when I give a manager a hard copy he can see all the information he needs to see and only has to assign persons to tasks.
Is there a simple way to do this in a similar fashion??
Regards
Brian
4 replies
Oldest firstLog in or join to reply