Stop activity splitting over a non-working period

Al MacLeodMember for 19 years 8 months
Created
17
4
0

Hi,

I have an activity 4hrs in duration that needs to be completed within one working period (08hrs - 17hrs). Currently I have it on a calendar with non-working time (17hrs - 08hrs). If the activity starts too late (say at 15hrs on day one) it is split over the non-working period and completed in the second day at 10hrs. How do I stop the activity starting on the first day and moving it so that it starts and finishes (08hrs to 12hrs) on the second day.

Thanks in advance for your help

17 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    use Suspend and resume

    use Suspend and resume 

  2. 0
    Al MacLeod ·

    Hi,Suspend and resume only

    Hi,

    Suspend and resume only work when you are progressing an activity. I want to be able to schedule my plan and see the activities in the future in the correct working periods and not split. I have a series of these activities that i do not want split.

  3. 0
    Vladimir Liberzon ·

    This functionality exists

    This functionality exists only in Spider Project.

  4. 0
    Zoltan Palffy ·

    then make seperate

    then make seperate activities 

  5. 0
    David Kelly ·

    Al,  The activities must

    Al,

     

     

    The activities must start between 08:00 and 13:00 in order to complete the same day. So this is a "resource levelling" task.

    You need a dummy resource that is only available for those hours of the day, and you level (perhaps ONLY this resource if you do not normally level) against an avvailability that only runs from 08:00 to 13:00.

    Ugly, but it works.

    Have fun.

    david

     

  6. 0
    David Kelly ·

    Vladimir,Let me use my

    Vladimir,

    Let me use my fingers to count on. This is an important skill for Primavera users.

    My fingers have let me down, I can't map 12:59hrs to a finger. I shall start P6........

  7. 0
    Vladimir Liberzon ·

    David,an activity can be

    David,

    an activity can be scheduled to start on 12:00 and to finish on 16:00. With your solution an activity will be delayed and will start only on 08:00 next day. This delay is not required.

    I expect that P6 does not plan activity execution on resource non-working time (after 13:00) but let me know if I am wrong. There are many amazing features in P6.

  8. 0
    David Kelly ·

    Vladimir, Not forgotten. My

    Vladimir,

     

    Not forgotten. My leveling solution does work, but I may have found a simpler one. It's still ugly compared to being able to define an activity as "un-splittable". I shall revert after this wonderful week-end. Glasgow where I currently live is hotter and sunnier than it has been for more than a hunderd years.

    D

  9. 0
    Vladimir Liberzon ·

    Thank you David!I am really

    Thank you David!

    I am really interested in the solutions that you suggest.

    And please explain why your initial proposal works despite the time after 13:00 is non-working for assigned resource.

    By the way in Spider Project an activity is splittable if assigned resource may be temporarily moved to activity with higher priority or if splitting improves project schedule. An activity is continious if it shall finish before work day end. So splittable (or not) and continuous (or not) are different activity properties.

     

    Best Regards,

    VL

  10. 0
    Al MacLeod ·

    Hi David,I have tried

    Hi David,

    I have tried creating the calendar for a resource with the buffer time as non working. I have set the activity to resource dependant and levelled the resource.

    When the activity starts at 12:00 it shows 2 hours work then 2 hours then next day. I need it to show all 4 hours then next day.

    Is there something im missing?

    Thanks

    Al

  11. 0
    David Kelly ·

    Gosh, Al, given that there is

    Gosh, Al, given that there is a four-year gap in this thread’s activities, does that count as ‘suspend/resume’? As we all know, P6’s mathematics isn’t very good. Indeed, it has the worst algorithms of any project management system I have used in a production environment. I specify ‘production environment’ because: 1) I have never used Microsoft Project in a production environment 2) I have tested ‘P6 Cloud’ I continue to be amazed that planners use a planning system that cannot control splitable activities. I had perfectly good control with Project 2 and K&H in the 1970s. But enough therapeutic ventilating. My current ‘best’ solution for this is to add a predecessor for each ‘un-splitable’ activity which is one hour long, and needs a dummy resource which is only available in your example from 08:00 to 09:00 and from 13:00 to 14:00. Then level. Four years ago, I thought I had a solution that placed the same dummy resource on only period one of the un-splitable activity, but the P6 levelling is incredibly unreliable if you have resource lag and duration specified in an activity. I got some lucky results, but just far too flaky to use. Of course, you can easily filter out the predecessors when printing. You will find entering the resource dictionary very time-consuming. It would be amusing to compare the cost of entering the resource dictionary at your current rate with the cost of Spider Project………
  12. 0
    David Kelly ·

    Gosh, Al, given that there is

    Gosh, Al, given that there is a four-year gap in this thread’s activities, does that count as ‘suspend/resume’? As we all know, P6’s mathematics isn’t very good. Indeed, it has the worst algorithms of any project management system I have used in a production environment. I specify ‘production environment’ because: 1) I have never used Microsoft Project in a production environment 2) I have tested ‘P6 Cloud’ I continue to be amazed that planners use a planning system that cannot control splitable activities. I had perfectly good control with Project 2 and K&H in the 1970s. But enough therapeutic ventilating. My current ‘best’ solution for this is to add a predecessor for each ‘un-splitable’ activity which is one hour long, and needs a dummy resource which is only available in your example from 08:00 to 09:00 and from 13:00 to 14:00. Then level. Four years ago, I thought I had a solution that placed the same dummy resource on only period one of the un-splitable activity, but the P6 levelling is incredibly unreliable if you have resource lag and duration specified in an activity. I got some lucky results, but just far too flaky to use. Of course, you can easily filter out the predecessors when printing. You will find entering the resource dictionary very time-consuming. It would be amusing to compare the cost of entering the resource dictionary at your current rate with the cost of Spider Project………
  13. 0
    Paul Kral ·

    Have you tried preceding the

    Have you tried preceding the activity with a start MS that's on a separate calendar that only allows work in the first 4 hours of the day (e.g. 8-12). Then if the succeeding activity in on an 8 hour calendar (e.g. 8-12; 13-18) with maximum duration 4 hours, it can only be completed the same day, if it starts in the first 4 hours of the day.

  14. 0
    Paul Kral ·

    Have you tried preceding the

    Have you tried preceding the activity with a start MS that's on a separate calendar that only allows work in the first 4 hours of the day (e.g. 8-12). Then if the succeeding activity in on an 8 hour calendar (e.g. 8-12; 13-18) with maximum duration 4 hours, it can only be completed the same day, if it starts in the first 4 hours of the day.

  15. 0
    Paul Kral ·

    Have you tried preceding the

    Have you tried preceding the activity with a start MS that's on a separate calendar that only allows work in the first 4 hours of the day (e.g. 8-12). Then if the succeeding activity in on an 8 hour calendar (e.g. 8-12; 13-18) with maximum duration 4 hours, it can only be completed the same day, if it starts in the first 4 hours of the day.

  16. 0
    Paul Kral ·

    Try adding a start MS to the

    Try adding a start MS to the activity. Put the MS on a calendar that restricted to the 1st 4 hours of the day. Then activity will always be completed the same day as started, provided dur is max 4 hours.

  17. 0
    Paul Kral ·

    Try adding a start MS to the

    Try adding a start MS to the activity. Put the MS on a calendar that restricted to the 1st 4 hours of the day. Then activity will always be completed the same day as started, provided dur is max 4 hours.

Log in or join to reply