Exporting P3e with Baselines

Keith FisherMember for 21 years
Created
1
3
0
I am using P3e Ver 4.1 and need to send a baselined plan to the client.

From what i have read and listened to colleges this appears to be a very long winded exercise by splitting the plan up and sending it in parts for the client to put back together, my concerns are that the data will be the same once it is put back together.

Is there a simpler, safer way of exporting a plan with a baseline. I assume this will also apply to recourses, costs etc

1 reply

Oldest first
  1. 0
    David Kelly ·
    The only way to export a plan with it’s baseline is to restore the baseline first, then export both plans. On receipt of two projects, the baseline can be demoted to a baseline again by using the "convert another peoject" option in the baselines dialog

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?