Logic Links and Baselines

Emma SeatonMember for 21 years 1 month
Created
9
9
0

Can anyone shed any light on this:

When I’m using the networked P3e and I have baselines showing all the logic links are shown as being between the baseline bars. However, when using my standalone version the logic is correctly shown as against the current activity bars. I don’t see anything obvious in the few option selections available.

Can anyone suggest why this might be and what the fix is? It makes it difficult to read when the logic is against the baseline bars. I’m not the network version administrator, but I’d like to be able to suggest a solution to them.

Emma

9 replies

Oldest first
  1. 0
    Emma Seaton ·
    Mario

    Thanks - that’s brilliant: I might have guessed it was something simple, but it’s just another one of those little things you don’t get told about in training unless you happen to ask, and even then it depends on someone else happening to know.

    I shall be sharing this nugget with my colleagues....
  2. 0
    Amar Aghana ·
    Hi guys,

    I too have similar problem.

    I use p3 e&c ver 4.1

    The relationship link lines are shown between baseline activities.

    When we progress on project, the relationship and the logic normally changes.

    That is why, I prefer to have relationship lines betwen activities of the current bar.

    Where to set this please?
  3. 0
    Amar Aghana ·
    Mario, I have current bar above baseline. I have switched Relationship line off and on. But still, the relationship lines are shown for baseline only.
  4. 0
    Amar Aghana ·

    Sorry, Mario.

    I was referring to Gantt Chart only. Now it is working fine. Thanks.
  5. 0
    Emma Seaton ·
    Amar, Mario’s right...but you need to right click on the bars in the activity screen and select ’bars’ in the menu shown. Then select the baseline bar in the bars dialogue box and hit the ’move down’ button until you see it move below the current bar in the list.... in fact just to be really sure, move it right to the bottom of the list, along with the baseline milestones.

    Emma
  6. 0
    Emma Seaton ·
    Ah, looks like you’ve sussed it already - our posts crossed!
  7. 0
    Amar Aghana ·
    Emma, It is okay. Thanks for your participation and support.
  8. 0
    Frank Neal ·

    Hi Mario... this is a simple

    Hi Mario...

     

    this is a simple fix...

     

    Click on the bars tab at the top ( where you format all your bars, thickness, colurs, etc..

     

    the links depend on the position of your bars in the drop down list..

     

    if your baseline formatted bar is above your current bar the links are shown for baseline, just move your baseline bar below your current bar and the links will show on your current bar.

     

    Good luck

  9. 0
    Raymund de Laza ·

    Frank, Mario may not see

    Frank,

    Mario may not see anymore your response because its been almost a decade ago when the problem arise.

    Wed, 2005-09-28 05:41

Log in or join to reply