Logic Links and Baselines
- Created
- 9
- 9
Can anyone shed any light on this:
When I’m using the networked P3e and I have baselines showing all the logic links are shown as being between the baseline bars. However, when using my standalone version the logic is correctly shown as against the current activity bars. I don’t see anything obvious in the few option selections available.
Can anyone suggest why this might be and what the fix is? It makes it difficult to read when the logic is against the baseline bars. I’m not the network version administrator, but I’d like to be able to suggest a solution to them.
Emma
9 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?