V5 Problems : Layout and Activity Codes
In the Open Standard
Amar AghanaMember for 21 years 2 months
- Created
- 8
- 5
0
Friends,
I have created an activity code. Say "Location" with values L1, L2 and Other.
I have say 3 activities. Say A1, A2 and A3
I assign
Activity A1 > Location L1
Activity A2 > Location L2
Activity A3 > Location : I keep blank intentionally.
Now when I group and sort, the group ban for activity A3 showing "No Location"
How to keep this band blank as used to be in P3 by default.
Thanks, Amar.
I have created an activity code. Say "Location" with values L1, L2 and Other.
I have say 3 activities. Say A1, A2 and A3
I assign
Activity A1 > Location L1
Activity A2 > Location L2
Activity A3 > Location : I keep blank intentionally.
Now when I group and sort, the group ban for activity A3 showing "No Location"
How to keep this band blank as used to be in P3 by default.
Thanks, Amar.
8 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?