V5 : Activity Details >Resoruce Tab

Amar AghanaMember for 21 years 2 months
Created
0
2
0
Friends,

I have V5 set with all resources and Price/Unit filled in.

When I import a project having no actuals, from P3, Resource/time, Price/Unit are showing something wrong.

Resource / TIme: Some activities are with 0%, some with 18%, some with 100%

Price / Unit: The imported activities are having different price / Unit instead of taking what is set in global price/unit.

Also, I have an activity A and B both with durations 2 Days.
I have given relations A FF 2 B means B is completing after 2 days of completion of A.

But after scheduling A and B are completing on same day.

What to do??