V5 : Activity Details >Resoruce Tab
In the Open Standard
Amar AghanaMember for 21 years 2 months
- Created
- 0
- 2
0
Friends,
I have V5 set with all resources and Price/Unit filled in.
When I import a project having no actuals, from P3, Resource/time, Price/Unit are showing something wrong.
Resource / TIme: Some activities are with 0%, some with 18%, some with 100%
Price / Unit: The imported activities are having different price / Unit instead of taking what is set in global price/unit.
Also, I have an activity A and B both with durations 2 Days.
I have given relations A FF 2 B means B is completing after 2 days of completion of A.
But after scheduling A and B are completing on same day.
What to do??
I have V5 set with all resources and Price/Unit filled in.
When I import a project having no actuals, from P3, Resource/time, Price/Unit are showing something wrong.
Resource / TIme: Some activities are with 0%, some with 18%, some with 100%
Price / Unit: The imported activities are having different price / Unit instead of taking what is set in global price/unit.
Also, I have an activity A and B both with durations 2 Days.
I have given relations A FF 2 B means B is completing after 2 days of completion of A.
But after scheduling A and B are completing on same day.
What to do??
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?