Skip to content

Compare progress

Marcio SampaioMember for 20 years 11 months
Created
3
1
0
Dear all,

Just to know if i’m using right columns to compare planned progress with actual progress. I select "Bl Activity % Complete" and " Activity % Complete".

I think it’s correct - by the explanation on "hint help" - but i’m in doubt becouse of explanation of "Bl Physical (Units / Duration) % Complete" that says:

"... The Physical (Units / Duration) percent complete reflects the actual progress made on activity’s work product so far ..."

Sorry, but i can’t understand this explanation by "hint help".

Do anyone have some comment about it?

Regards.

Marcio Eduardo

3 replies

Oldest first
  1. 0
    Amar Aghana ·
    Marcio,

    I too had same problem. When you change Activity % Complete, based % Completion type (Physical / Duration / Units), the appropriate % will be considered.


    For eg, if an activity % Completion type is Physical when you enter Activity % Complete as 5%, Physical % = 5%,


    But I am not able to understand how you have % Complete in Baseline.

    Regards, Amar.
  2. 0
    Amar Aghana ·
    Marcio, there is one more thing to understand. That is Performance % Complete. Please try and understand. I have some tips. But I am experimenting. Let me share with you once I am sure. Thanks, Amar.
  3. 0
    Marcio Sampaio ·
    Amar,

    I understand that Bl activity % Complete is how much activity must have progressed - until the actual data-date - based on baseline.

    If it’s correct, i can use it like a planned progress and compare with "Activity % Complete".

    Tell me if u agree.

    Regards.

    Marcio Eduardo

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?