Resource progress (v.5.0).

Marcio SampaioMember for 20 years 11 months
Created
3
3
0
Dear all,

I heard that when u give progress to activities - on V.5 - resources are not automatically progressing.

Dp u know something about it?

Regards.

Marcio Eduardo.

3 replies

Oldest first
  1. 0
    Rajeev Nelliyodan ·
    Try clicking on "Recalculate Actual Units and Cost when duration % complete changes" under calculation tab in Project view.
  2. 0
    Marcio Sampaio ·
    Ok.

    I’ll try it and return to u results.

    Regards.

    Marcio Eduardo
  3. 0
    Marcio Sampaio ·
    Rajeev,

    The option is select. But resources are still not automatically progressing.

    I’m afraid it’s something new on V.5 (or a bug). Better return to P3e v.4.1

    Regards.

    Marcio Eduardo.