Leveling in P3 e/c

Stephen Fawcett-JonesMember for 20 years 10 months
Created
1
2
0
When using the leveling tool in P3 e/c the client I work for use the "preserve schedule early and late dates" option. If we are working to leveled dates and not the early start dates surely this should be unmarked to give the true total float. I have tried both methods within the schedule and both results are very different. My question is should this be marked or unmarked ? I am trying to find out which is the correct method. I believe it should be unmarked to give the total float based on the new leveled dates. Any replies would be grateful

Cheers

1 reply

Oldest first
  1. 0
    Stephen Fawcett-Jones ·
    Thanks for the reply Bob, I have managed to resolve the levelling issue (I was right). But the client is insisting on using the early preserve dates, so I have to agree to disagree and get on with it

    Cheers

    Steve

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?