Resource Profile Selection

Mike ParsonsMember for 20 years 10 months
Created
2
4
0
I remember being able to select and display several resources that would display "stacked" in various colors in the resource profile/table in P3. I can’t seem to find it in P3ec. What I am really after is being able to print a schedule showing all resources required in graphic form. My schedule has about 12 resources. Any ideas? Thanks.

2 replies

Oldest first
  1. 0
    Kevin Button ·
    Mike

    With the Resource Usage Profile displayed, right click on the profile and select ’Stacked Histogram’. Then right click again and select ’Resource Usage Profile Options’ and here you build your filters for the various resources and colours in the stack. You wil also need to right click and uncheck the ’Show All Projects’ option if yo want to display resource usage for the open project only.

    Cheers

    KB
  2. 0
    Mike Parsons ·
    Thank you.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?