Fiscal Year Info in Activities View - Columns
In the Open Standard
Richard RowberryMember for 23 years 6 months
- Created
- 1
- 2
0
Folks,
I’m trying to get a roll-up of fiscal year information in column format in Activities view. (ie I have £xyz budgeted labour cost spread by fiscal year in resource tabular format by setting the timescale to fiscal, but would like to create a user defined column that will show budgeted cost by fiscal year);
1) Is this possible?
2) If so, how,
Any ideas welcomed
Richard Rowberry
Planning & Control Lead
Nuclear Sector
I’m trying to get a roll-up of fiscal year information in column format in Activities view. (ie I have £xyz budgeted labour cost spread by fiscal year in resource tabular format by setting the timescale to fiscal, but would like to create a user defined column that will show budgeted cost by fiscal year);
1) Is this possible?
2) If so, how,
Any ideas welcomed
Richard Rowberry
Planning & Control Lead
Nuclear Sector
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?