Skip to content

HOW CAN I MAKE CALENDER

Tamer SayedMember for 20 years 8 months
Created
16
6
0
PLEASE HELP ME IN THIS CASE
I USE PRIMAVERA ENTERPRICE
AND THERE ARE DEFULT IN CALENDER IN SHEFT ( 6 DAYS × 8 HOURS )
I WANT TO CHANGE IT TO
7 DAYS × 24 HOURS
I ALREADY CHANGE IT TO NEW CALENDER BUT THE DURATION NOT CORRECT
AND THERE ARE CHECL MARK IN THE DEFULT SHEFT
PLEASE HELP ME
THANK YOU

16 replies

Oldest first
  1. 0
    Marcio Sampaio ·
    Tamer,

    See thread "WBS calendar"

    Regards.
  2. 0
    Tamer Sayed ·
    i can not find any solution for my question
    please tell me steps
    thank you
  3. 0
    Julie Scully ·
    Tamer

    You will need to assign this new 24x7 calendar as the default calendar for the project for new activities to automatically have it assigned. You will also need to change the calendar assigned to each of your existing activities; either by adding the calendar column to your view and filling down, or doing a global change.

    Cheers
    Julie
  4. 0
    Tamer Sayed ·
    dear / Julie Scully
    could you please tell me steps in detalies
    i am new in primavera enterprice
    and this case is very comflect
    please tell me frist do that , second do that , third do that
    also please tell me criteria in global change
    thank you
  5. 0
    Emma Seaton ·
    I’ve found a similar problem. I have a calendar which is 10 hrs x 7 days and cannot get the durations to calculate properly (I get strange start and finish hours, with activities spread over 3.5 instead of 2 days, for example. I’ve tried changing the settings under User Preferences, but this doesn’t really work as it affects activities on other calendars, and of course it affects other projects.

    Do I have to change other calendars elsewhere, such as WBS or project? None of which makes sense - surely if I specify a calendar to an activity it should override any defaults. It works fine when I use other calendars, such as for railway possessions which are often strange hours overnight at weekends!!

    Looking forward to hearing from anyone!

    Emma
  6. 0
    Marcio Sampaio ·
    Create a resource;

    Create a resource shift with 1 shift 24 hrs;

    Assign this resource to activities;

    Actvity Type = Resource Dependent.

    Think thats it, hope it works.

    Regards.
  7. 0
    Julie Scully ·
    You also need to be aware of the global ’Time Period’ settings under ’Admin Preferences’. The duration entered (in days) is worked out (in hours) using the Admin Preferences and converted back to a duration using the activity calendar.

    For example:
    Global Time periods are set to 24h/d, 7d/wk etc.
    No resources, activities are task dependent.

    EXAMPLE 1 - 8hrs x 5d Calendar
    Duration entered=5days=24*5=120hrs. Based on 8x5 the duration will be 15days, excluding weekends (120/8)
    Start=20/2/06
    Finish=10/3/06

    EXAMPLE 2 - 10hrs x 7d Calendar
    Duration entered=5days=24*5=120hrs. Based on 10x7 the duration will be 12days, including weekends (120/10)
    Start=20/2/06
    Finish=3/3/06

    Hope this helps.
    Cheers
    Julie
  8. 0
    Tamer Sayed ·
    DEAR /A LL
    I already done all this steps but problem still .
    I want to tell you problem in details
    First I create new calendar 24*7 days and done new tasks with new calendar
    Example :-
    First task 24 hours ( that mean this will stay 1 day )
    After that when I go to user preference to change hour to day
    24 hours appear = 3 days ( that mean 1 days =8 hours )
    This is problem
    I create calendar 24 hours per day but system use default calendar 8 hours per day
    This is problem
    In another side I go to defult to set new calendar but problem still
    24 hours = 3 days
    And I want
    24 hours = 1 day


    Another problem original duration
    When I create some steps and I want to see summation of all duration of this tasks in main original duration
    But I found number in original duration is not correct
    Could you solve me this problem
    Thank you






  9. 0
    Emma Seaton ·
    Interesting to hear that someone else has the same problem with the durations when changing calendars. In my view the calendar selected should override all other time settings. Is this a fault that should be reported to Primavera, if not done already?
  10. 0
    vito Kooij, van ·
    the problem can be solved by chance settings in user preferences.

    Actions> go to [edit]>[user preferences] tab[time units] then under [Durations format] and set unit of time to [Hour].

    you will see now that od of 24 hrs = one day.

    tis problem is caused by your settings in [units per time period] you can change it in admin pref’s (primavera use this as a conversion rule for calculate differend units back to hr’s. every project is calculated to hrs in the background of the database)

    hope this is usefull.
    greetz vito
  11. 0
    Tamer Sayed ·
    COOULD YOU TELL ME HOW CAN I WILL CONTACT WITH ADMIN TO CHANGE DURATION
    I WANT TO SEE
    24= 1 DAY
    BUT IN MY PROJECT
    24 HOURS = 3 DAYS
    THAT MEAN 8 DAYS PER DAY ONLY ( SHIFT = 8 HOURS )
    AND I WANT SHIFT = 24 HOURS
    I CHANGED CALENDER TO 24* 7
    BUT THE SAME PROPLEM FACED ME
    ALSO I DO DEFULT FOR MY CALENDER 24*7
    BUT I FIND
    24= 3 DAYS
    THANK YOU
  12. 0
    vito Kooij, van ·
    to change "hours per time period" you need to be logged in as admin and go to [admin]>[admin preferences]> tab [time periods] then you can do what ever you want.

    this is all! (see more ad nr: #11)
  13. 0
    Marcio Sampaio ·
    But remember ... doing it ... u will chenge all projects!!!
  14. 0
    vito Kooij, van ·
    correct!

    tnx
  15. 0
    Tamer Sayed ·
    if i want to change only one project what i will do
  16. 0
    Tamer Sayed ·
    also i wark in net work ani i trayed many time to change hour per day to 24
    but i can not
    it is fixed on 8 hours per day
    could you tell me what can i do

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?