HOW CAN I MAKE CALENDER
In the Open Standard
TS
Tamer SayedMember for 20 years 8 months
- Created
- 16
- 6
0
PLEASE HELP ME IN THIS CASE
I USE PRIMAVERA ENTERPRICE
AND THERE ARE DEFULT IN CALENDER IN SHEFT ( 6 DAYS × 8 HOURS )
I WANT TO CHANGE IT TO
7 DAYS × 24 HOURS
I ALREADY CHANGE IT TO NEW CALENDER BUT THE DURATION NOT CORRECT
AND THERE ARE CHECL MARK IN THE DEFULT SHEFT
PLEASE HELP ME
THANK YOU
I USE PRIMAVERA ENTERPRICE
AND THERE ARE DEFULT IN CALENDER IN SHEFT ( 6 DAYS × 8 HOURS )
I WANT TO CHANGE IT TO
7 DAYS × 24 HOURS
I ALREADY CHANGE IT TO NEW CALENDER BUT THE DURATION NOT CORRECT
AND THERE ARE CHECL MARK IN THE DEFULT SHEFT
PLEASE HELP ME
THANK YOU
16 replies
Oldest first- 0JSJulie Scully ·Tamer
You will need to assign this new 24x7 calendar as the default calendar for the project for new activities to automatically have it assigned. You will also need to change the calendar assigned to each of your existing activities; either by adding the calendar column to your view and filling down, or doing a global change.
Cheers
Julie - 0ESEmma Seaton ·I’ve found a similar problem. I have a calendar which is 10 hrs x 7 days and cannot get the durations to calculate properly (I get strange start and finish hours, with activities spread over 3.5 instead of 2 days, for example. I’ve tried changing the settings under User Preferences, but this doesn’t really work as it affects activities on other calendars, and of course it affects other projects.
Do I have to change other calendars elsewhere, such as WBS or project? None of which makes sense - surely if I specify a calendar to an activity it should override any defaults. It works fine when I use other calendars, such as for railway possessions which are often strange hours overnight at weekends!!
Looking forward to hearing from anyone!
Emma - 0JSJulie Scully ·You also need to be aware of the global ’Time Period’ settings under ’Admin Preferences’. The duration entered (in days) is worked out (in hours) using the Admin Preferences and converted back to a duration using the activity calendar.
For example:
Global Time periods are set to 24h/d, 7d/wk etc.
No resources, activities are task dependent.
EXAMPLE 1 - 8hrs x 5d Calendar
Duration entered=5days=24*5=120hrs. Based on 8x5 the duration will be 15days, excluding weekends (120/8)
Start=20/2/06
Finish=10/3/06
EXAMPLE 2 - 10hrs x 7d Calendar
Duration entered=5days=24*5=120hrs. Based on 10x7 the duration will be 12days, including weekends (120/10)
Start=20/2/06
Finish=3/3/06
Hope this helps.
Cheers
Julie - 0TSTamer Sayed ·DEAR /A LL
I already done all this steps but problem still .
I want to tell you problem in details
First I create new calendar 24*7 days and done new tasks with new calendar
Example :-
First task 24 hours ( that mean this will stay 1 day )
After that when I go to user preference to change hour to day
24 hours appear = 3 days ( that mean 1 days =8 hours )
This is problem
I create calendar 24 hours per day but system use default calendar 8 hours per day
This is problem
In another side I go to defult to set new calendar but problem still
24 hours = 3 days
And I want
24 hours = 1 day
Another problem original duration
When I create some steps and I want to see summation of all duration of this tasks in main original duration
But I found number in original duration is not correct
Could you solve me this problem
Thank you
- 0VKvito Kooij, van ·the problem can be solved by chance settings in user preferences.
Actions> go to [edit]>[user preferences] tab[time units] then under [Durations format] and set unit of time to [Hour].
you will see now that od of 24 hrs = one day.
tis problem is caused by your settings in [units per time period] you can change it in admin pref’s (primavera use this as a conversion rule for calculate differend units back to hr’s. every project is calculated to hrs in the background of the database)
hope this is usefull.
greetz vito - 0TSTamer Sayed ·COOULD YOU TELL ME HOW CAN I WILL CONTACT WITH ADMIN TO CHANGE DURATION
I WANT TO SEE
24= 1 DAY
BUT IN MY PROJECT
24 HOURS = 3 DAYS
THAT MEAN 8 DAYS PER DAY ONLY ( SHIFT = 8 HOURS )
AND I WANT SHIFT = 24 HOURS
I CHANGED CALENDER TO 24* 7
BUT THE SAME PROPLEM FACED ME
ALSO I DO DEFULT FOR MY CALENDER 24*7
BUT I FIND
24= 3 DAYS
THANK YOU