wbs activity
In the Open Standard
Sunil KumarMember for 21 years
- Created
- 1
- 1
0
I had created a p3 schedule which consists of 1000 activities, and organised it.
Then i created WBS activities which shows the summary of the group of activities.
Now my Problem is i want to assign this wbs activites as relations to some other activities , but p3 is not taking it. Please suggest in this regard.
cos of this Total float - i m getting very big digits which is not acceptable pratically........
please suggest a solution for this????
1 reply
Oldest firstLog in or join to reply