wbs activity

Sunil KumarMember for 21 years
Created
1
1
0

I had created a p3 schedule which consists of 1000 activities, and organised it.

Then i created WBS activities which shows the summary of the group of activities.

Now my Problem is i want to assign this wbs activites as relations to some other activities , but p3 is not taking it. Please suggest in this regard.

cos of this Total float - i m getting very big digits which is not acceptable pratically........
please suggest a solution for this????

1 reply

Oldest first
  1. 0
    Paul Harris ·
    A WBS activity by the nature of being a WBS activity spans all other activities with the same WBS code.

    The relationships need to go from the non WBS activities.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au