Activity usage spreadsheet

Shahzad SikandarMember for 20 years 8 months
Created
2
4
0
Hi guys,

Do any one how i can transfer activity usage spreadsheet items to excel? Lets say i need following in my excel.

1.resource name and its associated activity
2.Bugeted units
3.Planned start and finish of resource
4.start and finsih of activity

2 replies

Oldest first
  1. 0
    Julie Scully ·
    It may be easier to use the resource assignments, which is very similar to the activity usage spreadsheet. Once you have all the columns etc in you layout, you can simply copy and paste the resource assignments. I don’t think this option is available in the activity usage spreadsheet. The other option is to create a report and output it to a csv file and open with excel.

    HTH
    Julie
  2. 0
    Kym Lesinski ·
    I find the easiest way to get info into excel is using a report. They’re very useful once you figure out how to set them up.