Skip to content

Out of Sequence activities

Kannan PalaniappanMember for 20 years 3 months
Created
4
1
0
I have plan with more than 40000 activities. I need to extract list of activities that are out of sequence after scheduling. Can any one let me know what parameters do I choose (in filter) in order to extract the list.

4 replies

Oldest first
  1. 0
    Marcio Sampaio ·
    Kannan,
    Don’t think u can create a filter like this.
    U have to schedule your project to see if there is any out of sequence activity.
    Regards.
  2. 0
    Marcio Sampaio ·
    using your subject ...

    what is the diference between out of sequnece activities and activities with unsatisfied relationships?

    regards.
  3. 0
    Rashid Iqbal ·
    Kannan

    You make a baseline, change the scheduling setting to ’progress override’ and then compare the finish date of the activties that are already started with the baseline dates. Populate a UDF saying "Out of Sequence" via global change and this will give you the ability to filter the activties.

    Or just read the schedule log and hunt those activties down.

    Regards
    Rashid



  4. 0
    Marcio Sampaio ·
    keep it simple ... "Or just read the schedule log and hunt those activties down"

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?