Hi everybody,
I am a past profound user of this forum. Recently been migrated to P3e/c. I am facing the following problems.
Problem # 1.
In P3 3.1 we could easily add/assign resources to hundereds of activities by applying global change parameter "Resource, "AD", Resource ID.
e.g.
If Activity Code = (certain code)
Then Resource AD Resrouce ID/name
Else
In P5 there is no AD (abbriviation of ADD) parameter but only "=" parameter. If we use the following to add a resource to multiple activities passing certain filter criteria, it wouldn’t add anything if the activities have no prior resource assignments.
If a filter = (filter condition)
Then Resrouce = Resource ID/Name
Else
But if the activities meeting this filter criteria have prior resource assignments then, the above global change would replace the resource to be added with existing ones!
Problem # 2;
Relationship lines on bar chart would join the baseline bars not the current project bars. It’s annoying as its confusing in visual comprehension of the layout.
Helpful comments from anybody are greatly appreciated.
Regards,
Zafar
I am a past profound user of this forum. Recently been migrated to P3e/c. I am facing the following problems.
Problem # 1.
In P3 3.1 we could easily add/assign resources to hundereds of activities by applying global change parameter "Resource, "AD", Resource ID.
e.g.
If Activity Code = (certain code)
Then Resource AD Resrouce ID/name
Else
In P5 there is no AD (abbriviation of ADD) parameter but only "=" parameter. If we use the following to add a resource to multiple activities passing certain filter criteria, it wouldn’t add anything if the activities have no prior resource assignments.
If a filter = (filter condition)
Then Resrouce = Resource ID/Name
Else
But if the activities meeting this filter criteria have prior resource assignments then, the above global change would replace the resource to be added with existing ones!
Problem # 2;
Relationship lines on bar chart would join the baseline bars not the current project bars. It’s annoying as its confusing in visual comprehension of the layout.
Helpful comments from anybody are greatly appreciated.
Regards,
Zafar
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?