Adding a resource to a project

Stephen OdomMember for 10 years 1 month
Created
25
10
0

Hello!

I'm using P6 to manage a non-resource loaded schedule and am attempting to add resources, but on the Resources tab, the option to create a resource is greyed out.

I have full permissions and am listed as an Administrator. The Security Profile Add/Edit/Delete priveleges are checked as well. The Display: All Resources shows no resources.

Any help is greatly appreciated!

Thanks!

25 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    What version are you using ?

    What version are you using ? Do you have global right or just project rights ?

  2. 0
    Stephen Odom ·

    Hi, sorry for the delay (just

    Hi, sorry for the delay (just turned on email notifications).

     

    I am listed as an administrator with the same security profile on Primavera P6 R15.1

     

    Under the security profiles, all administrator privileges are checked, including Add Resource.


    Thanks!

     

    Stephen

  3. 0
    Stephen Odom ·

    Hi, sorry for the delay (just

    Hi, sorry for the delay (just turned on email notifications).

     

    I am listed as an administrator with the same security profile on Primavera P6 R15.1

     

    Under the security profiles, all administrator privileges are checked, including Add Resource.


    Thanks!

     

    Stephen

  4. 0
    Zoltan Palffy ·

    is the project open ?

    is the project open ?

  5. 0
    Stephen Odom ·

    Yes

    Yes
  6. 0
    Zoltan Palffy ·

    try pressing the insert key

    try pressing the insert key and see what happens

  7. 0
    Stephen Odom ·

    The Add function is greyed

    The Add function is greyed out. Pressing Insert doesn't add the resource.

  8. 0
    Stephen Odom ·

    The Add function is greyed

    The Add function is greyed out. Pressing Insert doesn't add the resource.

  9. 0
    Zoltan Palffy ·

    try opening a project first

    try opening a project first 

  10. 0
    Stephen Odom ·

    The project is opened.

    The project is opened. Everything seems normal, but the function is not active.

  11. 0
    Stephen Odom ·

    The project is opened.

    The project is opened. Everything seems normal, but the function is not active.

  12. 0
    Johannes Vandenberg ·

    Hi StephenBefore you can add

    Hi Stephen

    Before you can add resources from the activity windows tab on the bottom of the screen, you have to make first a resource under the enterprise resource tab.

    After that, you add the resource to the activity in the activity window resource tab.

    If still grayed out, right click and select filter "all resources or project resources.

    Regards Johannes

  13. 0
    Stephen Odom ·

    Hi Johannes, That's where I

    Hi Johannes,

     

    That's where I am having my challenge. Inside the enterprise resouces display, I am unable to create a resource. It might be just something I am missing.

     

    Thanks!

     

  14. 0
    Johannes Vandenberg ·

    Hi StephenJust one more

    Hi Stephen

    Just one more try.

    As I can see you have access to the resources tab under Enterprise

    What happens when you click the +  button on the right-hand site of the screen or right-click and use insert.

    Regards Johannes

  15. 0
    Stephen Odom ·

    It's greyed out and not

    It's greyed out and not active; nothing happens. Is this normal? Is there a master setting I haven't unlocked?

     

    Thanks!

  16. 0
    Stephen Odom ·

    Still having issues creating

    Still having issues creating resources. 

     

    I am listed as an Administrator in P6 and have the priviledges to Add/Edit/Delet Users. Does this mean only inside of a project? Is there a level above Administrator that you guys are in that allow for creating resources?

  17. 0
    Zoltan Palffy ·

    you should be admin

    you should be admin superuser

    and all of the boxes should be checked under the security profile for Has Privilege

  18. 0
    Stephen Odom ·

    In my Users dialog box, no

    In my Users dialog box, no one is listed as an Admin Superuser. I have a few IT people and some coworkers, but they are all the same security profiles as me or lower...

     

  19. 0
    Zoltan Palffy ·

    all of the boxes should be

     all of the boxes should be checked under the security profile for Has Privilege

  20. 0
    Martin Thomson ·

    Hi , I had this issue as our

    Hi ,

     

    I had this issue as our primavera is set up across the company. Fixed it now with a bit of perseverance :) 

     

    I had to get our admin/superuser to go into Admin – Security profiles - Tick all privellages (which i think was mentioned earlier on this post) but after that i also had to go into Admin – Users - Global Access - Tick all resource access and now that has worked, my add resource button is no longer greyed out and i also have visibility of all our enterprise resources. 

    Ive attached a picture of the second task as its easy to miss the small box that needs ticked!

  21. 0
    Martin Thomson ·

    Hi , I had this issue as our

    Hi ,

     

    I had this issue as our primavera is set up across the company. Fixed it now with a bit of perseverance :) 

     

    I had to get our admin/superuser to go into Admin – Security profiles - Tick all privellages (which i think was mentioned earlier on this post) but after that i also had to go into Admin – Users - Global Access - Tick all resource access and now that has worked, my add resource button is no longer greyed out and i also have visibility of all our enterprise resources. 

    Ive attached a picture of the second task as its easy to miss the small box that needs ticked!

  22. 0
    Martin Thomson ·

    Hi , I had this issue as our

    Hi ,

     

    I had this issue as our primavera is set up across the company. Fixed it now with a bit of perseverance :) 

     

    I had to get our admin/superuser to go into Admin – Security profiles - Tick all privellages (which i think was mentioned earlier on this post) but after that i also had to go into Admin – Users - Global Access - Tick all resource access and now that has worked, my add resource button is no longer greyed out and i also have visibility of all our enterprise resources. 

    Ive attached a picture of the second task as its easy to miss the small box that needs ticked!

  23. 0
    Martin Thomson ·

    Hi , I had this issue as our

    Hi ,

     

    I had this issue as our primavera is set up across the company. Fixed it now with a bit of perseverance :) 

     

    I had to get our admin/superuser to go into Admin – Security profiles - Tick all privellages (which i think was mentioned earlier on this post) but after that i also had to go into Admin – Users - Global Access - Tick all resource access and now that has worked, my add resource button is no longer greyed out and i also have visibility of all our enterprise resources. 

    Ive attached a picture of the second task as its easy to miss the small box that needs ticked!

  24. 0
    Martin Thomson ·

    Hi , I had this issue as our

    Hi ,

     

    I had this issue as our primavera is set up across the company. Fixed it now with a bit of perseverance :) 

     

    I had to get our admin/superuser to go into Admin – Security profiles - Tick all privellages (which i think was mentioned earlier on this post) but after that i also had to go into Admin – Users - Global Access - Tick all resource access and now that has worked, my add resource button is no longer greyed out and i also have visibility of all our enterprise resources. 

    its easy to miss the small box that needs ticked!

  25. 0
    Martin Thomson ·

    Hi, I also had this same

    Hi,

     

    I also had this same issue but managed to fix it now.

     

    Needed to get our company administrator/superuser to go into - Users - Global Access - and tick the box that says "Specify the resources that the user will be able to access - All resource access" for your primavera account.

     

    Once done the add resource button was no longer greyed out and i was able to create resources