Resource allocation across different projects
In the Open Standard
Ly LuMember for 22 years 3 months
- Created
- 0
- 3
0
There are people who will be doing work on two different projects. For convenience, let’s say A’s time will be spent on Project 1 is 70% and Project 2 is 30%. I want to see the impact of allocating A to Project 2 in Project 1. e.g. will it delay Project 1 completion date? How do I do this in Primavera? I notice that I can’t use the calendar as the resource calendar will be used across different project. Do I change the Remaining Units/Time on each activity?
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?