Skip to content

P3e progress bar against baseline bar

Steve LawsonMember for 22 years 8 months
Created
2
3
0
can anyone advise me how to show the progress bar to reflect physical progress against the baseline bar, rather than the current bar, as it is doing by default, as this would be more what users expect to see, and more useful

Regards
Steve

2 replies

Oldest first
  1. 0
    Dayanidhi Dhandapany ·
    choose the "%complete bar" under the "TimeScale" column from the "Bars" option. Make %Complete Type as Physical from the GeneralTab of Activity Details Window.

    bye the way, is this the one you are expecting or something else?.
  2. 0
    Steve Lawson ·
    Thanks for that, but that is what i already have. that gives me a % progress bar against the current (actual & forecast bar. What I am after is the % complete bar against the baseline bar.

    eg if the baseline bar finishes in aug and the current is complete the progress bar finishes to the left of the data date.
    also if the end date of the baseline bar is past the progress bar can come past that enddate if the current is not complete. I find people like to track progress against a baseline (agreed plan, not against the current which is dynamic and always changing. your planned dates & planned progress figures also come from the baseline.
    Regards

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?