Skip to content

reset progress?

hans HOMember for 21 years 3 months
Created
3
2
0
Hi? Friends...
i’ve got some problem with reseting progress of my project in which actual has already been.
i mean many activities have actual start date, actual costs, something like that.
i ran global change tool to reset actual date out. but
the global change report showed that it "Cannot set status to Not Started if activity has actuals".
i need to get back my project to original in status.
What should i do. next?

Any comments regarding above will be appreciated.
Cheers! friends~~

3 replies

Oldest first
  1. 0
    Ronald Winter ·
    First globally delete the actual dates, then percent complete, and then the condition. Good luck!
  2. 0
    hans HO ·
    thanks Ronald.
    i’ll try~~..Cheers!
  3. 0
    David Forrest ·
    You need to remove the actual units. If an activity has actual units P3e automaticaly sets it as started!!!

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?