P3e Milestones - FYI

Nigel WinkleyMember for 20 years 5 months
Created
0
4
0
Hi All

Just had a goodie - 24 hour day, 7 days per week calendar.

Constrained a start milestone. Would not go to the correct day, always the day after.

I do not display times and this one had set itself to 17:00. So of course it would go to the next day.

So if you get a ’funny’ display the time and make sure that a start milestone starts at the beginning of the day! (Probably the opposite for Finish milestones.)

Ho hum...Nige’s law strikes again

Cheers

Nige