P3e Milestones - FYI
In the Open Standard
Nigel WinkleyMember for 20 years 5 months
- Created
- 0
- 4
0
Hi All
Just had a goodie - 24 hour day, 7 days per week calendar.
Constrained a start milestone. Would not go to the correct day, always the day after.
I do not display times and this one had set itself to 17:00. So of course it would go to the next day.
So if you get a ’funny’ display the time and make sure that a start milestone starts at the beginning of the day! (Probably the opposite for Finish milestones.)
Ho hum...Nige’s law strikes again
Cheers
Nige
Just had a goodie - 24 hour day, 7 days per week calendar.
Constrained a start milestone. Would not go to the correct day, always the day after.
I do not display times and this one had set itself to 17:00. So of course it would go to the next day.
So if you get a ’funny’ display the time and make sure that a start milestone starts at the beginning of the day! (Probably the opposite for Finish milestones.)
Ho hum...Nige’s law strikes again
Cheers
Nige
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?